Stuck Down Carpets – St Peters And St Pauls School Chaldon

Heckmondwike Supacord To Class Room
existing carpets ripped up
Existing carpets ripped up
Cracks filled with ardurapid
Cracks filled with ardurapid
Sub floor latexed
Sub floor latexed
Carpets rolled out and cut to length
Carpets rolled out and cut to length
Carpets stuck with F3
Carpets stuck with F3
Carpet seams overlapped and cut
Carpet seams overlapped and cut
Carpets completed
Carpets completed

A carpet refit to a library room at St Peters And St Pauls Chaldon Surrey.

Day 1 The existing green fibre carpets were taken up and removed. The sub floor was pretty clean with old residues of flooring adhesive left. The floors were then primed and latexed.

The following day new Heckmondwike Supacord fibre carpets in blue were fitted and stuck with F3 carpet adhesive. All in ample time for school opening the following day!